Sirohi : 95 percent work of the sewerage line started 4 years ago in Sirohi city has been completed. The work is said to be completed by December. After 15 years, the common people are facing problems due to poor sewerage work in the divisional headquarters Pali city. It has been 3 years since the sewerage work was completed. There is a problem of blockage of lines and dirty water coming out of the chamber. Due to sewerage chambers being above and below the road, accidents are happening at many places in the city. However, chambers have been arranged in Sirohi city after inspection by the Collector and MP last month. Dirty water will reach the treatment plant through the sewerage line. After the water is treated from the plant, it can be used in agriculture, washing of city roads and industrial works. If there is any problem or deficiency in sewerage work around you. If repair is not done even after repeated requests, WhatsApp us on 8952050729. Will present your problem in front of those responsible.
These colonies of the city have been connected: Amar Nagar, Balaji Colony First, Bhadrakar Nagar, Hariom Nagar, Housing Board Colony, Emmanuel School Colony, Income Tax Colony, Krishnakunj Colony, Laxmi Nagar, Mahakal Nagar, Meenawas, New Bus Stand Colony, Nehru. Nagar, Palace Road, Police Line, Radhika Nagar, Raj Nagar, Roopraj School, Sai Nagar, Shastri Nagar, Shanti Nagar, Saraneshwar Town Ship, Sewerage lines have been laid in almost all the colonies of the city including Swaroop Nagar, Vidyanath Colony and Vikanand Colony. Work is going on in some colonies. There are many colonies in the city where the roads have not been maintained after laying sewerage lines. There has been a problem of roads sinking during rains. After the sewerage lines are fully operational in the city, technical deficiencies in the lines may increase. {5 MLD treatment plant has been 100% completed
{1.7 MLD treatment plant is 99% complete
{Out of 82.318 kilometer sewerage line, 81.028 kilometer line has been laid so far.
{Out of 11002 chambers, 9648 chambers have been built.
{Out of 11002, 3741 connections have been given.
{The project of sewerage and 24 hours water supply is worth Rs 213.92 crore.
{Out of this, sewerage line and related works worth Rs 101 crore are being done.
{The work on the project started on 22 June 2020, it is to be completed by December 2024. There are some difficulties in laying the sewerage line due to the presence of stones in the lower part of the ground on Revdar Road in the city. Blasting cannot be done due to there being population nearby, engineers have installed machines to dig the stones. Work is being done through this. The work of laying the line will be completed in 20 to 25 days. 95 percent work has been completed, sewerage will be fully operational by the end of December. Due to hard rock at two places, the work of laying the line is going on. The project will be maintained for 10 years, the problems of common people will be removed. – Manish Arora, SE Rudeep Sirohi